Construction
Construction of the Brooklyn Bridge began on January 2, 1870. The first work entailed the construction of two caissons, upon which the suspension towers would be built. The Brooklyn side's caisson was built at the Webb & Bell shipyard in Greenpoint, Brooklyn, and was launched into the river on March 19, 1870. Compressed air was pumped into the caisson, and workers entered the space to dig the sediment until it sank to the bedrock. As one sixteen-year-old from Ireland, Frank Harris, described the fearful experience:The six of us were working naked to the waist in the small iron chamber with the temperature of about 80 degrees Fahrenheit: In five minutes the sweat was pouring from us, and all the while we were standing in icy water that was only kept from rising by the terrific pressure. No wonder the headaches were blinding. Once the caisson had reached the desired depth, it was to be filled in with vertical brick piers and concrete. However, due to the unexpectedly high concentration of large boulders atop the riverbed, the Brooklyn caisson took several months to sink to the desired depth. Furthermore, in December 1870, its timber roof caught fire, delaying construction further. The "Great Blowout", as the fire was called, delayed construction for several months, since the holes in the caisson had to be repaired. On March 6, 1871, the repairs were finished, and the caisson had reached its final depth of 44.5 feet (13.6 m); it was filled with concrete five days later. Overall, about 264 individuals were estimated to have worked in the caisson every day, but because of high worker turnover, the final total was thought to be about 2,500 men in total. Some workers were paralyzed by decompression sickness; at its final depth, the caisson's air pressure was 21 pounds per square inch (140 kPa).
The Manhattan side's caisson was the next structure to be built. To ensure that it would not catch fire like its counterpart had, the Manhattan caisson was lined with fireproof plate iron. It was launched from Webb & Bell's shipyard on May 11, 1871, and maneuvered into place that September. Due to the extreme underwater air pressure inside the much deeper Manhattan caisson, many workers became sick with "the bends"—decompression sickness—during this work, despite the incorporation of airlocks (which were believed to help with decompression sickness at the time). This condition was unknown at the time and was first called "caisson disease" by the project physician, Andrew Smith. Between January 25 and May 31, 1872, Smith treated 110 cases of decompression sickness, while three workers died from the disease. When iron probes underneath the Manhattan caisson found the bedrock to be even deeper than expected, Washington Roebling halted construction due to the increased risk of decompression sickness. After the Manhattan caisson reached a depth of 78.5 feet (23.9 m) with an air pressure of 35 pounds per square inch (240 kPa), Washington deemed the sandy subsoil overlying the bedrock 30 feet (9.1 m) beneath to be sufficiently firm, and subsequently infilled the caisson with concrete in July 1872.
Washington Roebling himself suffered a paralyzing injury as a result of caisson disease shortly after ground was broken for the Brooklyn tower foundation. His debilitating condition left him unable to supervise the construction in person, so he designed the caissons and other equipment from his apartment, directing "the completion of the bridge through a telescope from his bedroom." His wife, Emily Warren Roebling, not only provided written communications between her husband and the engineers on site, but also understood mathematics, calculations of catenary curves, strengths of materials, bridge specifications, and the intricacies of cable construction. She spent the next 11 years helping supervise the bridge's construction, performing much of the chief engineer's duties, including day-to-day supervision and project management.
After the caissons were completed, piers were constructed on top of each of them upon which masonry towers would be built. The towers' construction was a complex process that took four years. Since the masonry blocks were heavy, the builders transported them to the base of the towers using a pulley system with a continuous 1.5-inch-diameter (3.8 cm) steel wire rope, operated by steam engines at ground level. The blocks were then carried up on a timber track alongside each tower and maneuvered into the proper position using a derrick atop the towers. The blocks sometimes vibrated the ropes because of their weight, but only once did a block fall.
Construction on the suspension towers started in mid-1872, and by the time work was halted for the winter in late 1872, parts of each tower had already been built. By mid-1873, there was substantial progress on the towers' construction. The Brooklyn side's tower had reached a height of 164 feet (50 m) above mean high water (MHW), while the tower on the Manhattan side had reached 88 feet (27 m) above MHW. The arches of the Brooklyn tower were completed by August 1874. The tower was substantially finished by December 1874 with the erection of saddle plates for the main cables at the top of the tower. However, the ornamentation on the Brooklyn tower could not be completed until the Manhattan tower was finished. The last stone on the Brooklyn tower was raised in June 1875 and the Manhattan tower was completed in July 1876. The saddle plates atop both towers were also raised in July 1876. The work was dangerous: by 1876, three workers had died having fallen from the towers, while nine other workers were killed in other accidents.
When the towers were completed, they were taller than any building in the city, with the exception of the spire of Trinity Church, which reached 279 feet (85 m). This remained the case until 1890.
In 1875, while the towers were being constructed, the project had depleted its original $5 million budget. Two bridge commissioners, one each from Brooklyn and Manhattan, petitioned New York state lawmakers to allot another $8 million for construction. Ultimately, the legislators passed a law authorizing the allotment with the condition that the cities would buy the stock of Brooklyn Bridge's private stockholders.
Work proceeded concurrently on the anchorages on each side. The Brooklyn anchorage broke ground in January 1873 and was subsequently substantially completed in August 1875. The Manhattan anchorage was built in less time, having started in May 1875, it was mostly completed in July 1876. The anchorages could not be fully completed until the main cables were spun, at which point another 6 feet (1.8 m) would be added to the height of each 80-foot (24 m) anchorage.
The first temporary wire was stretched between the towers on August 15, 1876, using chrome steel provided by the Chrome Steel Company of Brooklyn. The wire was then stretched back across the river, and the two ends were spliced to form a traveler, a lengthy loop of wire connecting the towers, which was driven by a 30 horsepower (22 kW) steam hoisting engine at ground level. The wire was one of two that were used to create a temporary footbridge for workers while cable spinning was ongoing. The next step was to send an engineer across the completed traveler wire in a boatswain's chair slung from the wire, to show the workforce it was safe enough. The bridge's master mechanic, E. F. Farrington, was selected for this task, and an estimated crowd of 10,000 people on both shores watched him cross. A second traveler wire was then stretched across the span, a task that was completed by August 30. The temporary footbridge, located some 60 feet (18 m) above the elevation of the future deck, was completed in February 1877.
By December 1876, a steel contract for the permanent cables still had not been awarded. There was disagreement over whether the bridge's cables should use the as-yet-untested Bessemer steel or the well-proven crucible steel. Until a permanent contract was awarded, the builders ordered 30 short tons (27 long tons) of wire in the interim, 10 tons each from three companies, including Washington Roebling's own steel mill in Trenton, New Jersey. In the end, it was decided to use number 8 Birmingham gauge (approximately 4 mm or 0.165 inches in diameter) crucible steel, and a request for bids was distributed, to which eight companies responded. In January 1877, a contract for crucible steel was awarded to J. Lloyd Haigh, who was associated with bridge trustee Abram Hewitt, whom Roebling distrusted.
The spinning of the wires required the manufacture of large coils of it which were galvanized but not oiled when they left the factory. The coils were delivered to a yard near the Brooklyn anchorage. There they were dipped in linseed oil, hoisted to the top of the anchorage, dried out and spliced into a single wire, and finally coated with red zinc for further galvanizing. There were thirty-two drums at the anchorage yard, eight for each of the four main cables. Each drum had a capacity of 60,000 feet (18,000 m) of wire. The first experimental wire for the main cables was stretched between the towers on May 29, 1877, and spinning began two weeks later. All four main cables were being strung by that July. During that time, the temporary footbridge was unofficially opened to members of the public, who could receive a visitor's pass; by August 1877 several thousand visitors from around the world had used the footbridge. The visitor passes ceased that September after a visitor had an epileptic seizure and nearly fell off.
As the wires were being spun, work also commenced on the demolition of buildings on either side of the river for the Brooklyn Bridge's approaches; this work was mostly complete by September 1877. The following month, initial contracts were awarded for the suspender wires, which would hang down from the main cables and support the deck. By May 1878, the main cables were more than two-thirds complete. However, the following month, one of the wires slipped, killing two people and injuring three others. In 1877, Hewitt wrote a letter urging against the use of Bessemer steel in the bridge's construction. Bids had been submitted for both crucible steel and Bessemer steel; John A. Roebling's Sons submitted the lowest bid for Bessemer steel, but at Hewitt's direction, the contract was awarded to Haigh.
A subsequent wire sampling by Roebling's assistant engineers discovered that Haigh had substituted inferior quality wire in the cables. Of eighty rings of wire that were tested, only five met standards, and it was estimated that Haigh had earned $300,000 from the deception. At this point, it was too late to replace the cables that had already been constructed. Roebling determined that the poorer wire would leave the bridge only four times as strong as necessary, rather than six to eight times as strong. The inferior-quality wire was allowed to remain and 150 extra wires were added to each cable. To avoid public controversy, Haigh was not fired, but instead was required to personally pay for the extra higher-quality wire needed. The contract for the remaining wire was awarded to the John A. Roebling's Sons, and by October 5, 1878, the last of the main cables' wires went over the river.
After the suspender wires had been placed, workers began erecting steel crossbeams to support the roadway as part of the bridge's overall superstructure. Construction on the bridge's superstructure started in March 1879, but, as with the cables, the trustees initially disagreed on whether the steel superstructure should be made of Bessemer or crucible steel. That July, the trustees decided to award a contract for 500 short tons (450 long tons) of Bessemer steel to the Edgemoor (or Edge Moor) Iron Works, based in Philadelphia, to be delivered by 1880. The trustees later passed another resolution for another 500 short tons (450 long tons) of Bessemer steel. However, by February 1880 the steel deliveries had not started. That October, the bridge trustees questioned Edgemoor's president about the delay in steel deliveries. Despite Edgemoor's assurances that the contract would be fulfilled, the deliveries still had not been completed by November 1881. Brooklyn mayor Seth Low, who became part of the board of trustees in 1882, became the chairman of a committee tasked to investigate Edgemoor's failure to fulfill the contract. When questioned, Edgemoor's president stated that the delays were the fault of another contractor, the Cambria Iron Company, who was manufacturing the eyebars for the bridge trusses; at that point, the contract was supposed to be complete by October 1882.
Further complicating the situation, Washington Roebling had failed to appear at the trustees' meeting in June 1882, since he had gone to Newport, Rhode Island. After the news media discovered this, most of the newspapers called for Roebling to be fired as chief engineer, except for the Daily State Gazette of Trenton, New Jersey, and the Brooklyn Daily Eagle. Some of the longstanding trustees, including Henry C. Murphy, James S. T. Stranahan, and William C. Kingsley, were willing to vouch for Roebling, since construction progress on the Brooklyn Bridge was still ongoing. However, Roebling's behavior was considered suspect among the younger trustees who had joined the board more recently.
Construction on the bridge itself was noted in formal reports that Murphy presented each month to the mayors of New York and Brooklyn. For example, Murphy's report in August 1882 noted that the month's progress included 114 intermediate cords erected within a week, as well as 72 diagonal stays, 60 posts, and numerous floor beams, bridging trusses, and stay bars. By early 1883, the Brooklyn Bridge was considered mostly completed and was projected to open that June. Contracts for bridge lighting were awarded by February 1883, and a toll scheme was approved that March.
There was substantial opposition to the bridge's construction from shipbuilders and merchants located to the north, who argued that the bridge would not provide sufficient clearance underneath for ships. In May 1876, these groups, led by Abraham Miller, filed a lawsuit in the United States District Court for the Southern District of New York against the cities of New York and Brooklyn.
In 1879, an Assembly Sub-Committee on Commerce and Navigation began an investigation into the Brooklyn Bridge. A seaman who had been hired to determine the height of the span, testified to the committee about the difficulties that ship masters would experience in bringing their ships under the bridge when it was completed. Another witness, Edward Wellman Serrell, a civil engineer, said that the calculations of the bridge's assumed strength were incorrect. The Supreme Court decided in 1883 that the Brooklyn Bridge was a lawful structure.